Delta Precision Factory

Steel-framed production hall with heavy-duty flooring, compressed air and fire suppression.

Sector
Industrial
Location
10th of Ramadan
Duration
11 months
Delivered
2024

The challenge

Production equipment was already purchased and shipping, fixing the floor tolerances and service positions before the structural design was complete.

The solution

We reverse-engineered the layout from the equipment foundation drawings, poured a laser-screeded FM2 floor slab, and pre-installed service pits and anchor templates to the machine supplier's tolerances.

The result

Machinery was set on arrival with no grouting rework, saving an estimated six weeks of commissioning.